You have seen the terms TAB (Test and Balance) and HVAC Commissioning used on contractor websites and in specifications. They are related — both verify HVAC performance — but they are different services with different scopes. This page clarifies the difference so you can pick the right service for your project.
Test and Balance is the process of measuring airflow, water flow, and temperatures in an HVAC system, and adjusting the system to deliver design specifications. TAB is performed by a third-party agency (typically an AABC-certified or NEBB-certified firm) following standards like:
TAB covers:
TAB is required by spec on most mid- to large-sized HVAC jobs (commercial, institutional, multifamily) and is good practice on custom single-family homes.
TAB is a measurement activity. It confirms that the system delivers the design airflow but does not verify the rest of the design is correct.
Commissioning is a broader process that verifies the entire HVAC system was designed correctly and operates as intended. Commissioning follows a defined process typically documented in ASHRAE Guideline 0 and ASHRAE Standard 202 (for new buildings).
Commissioning covers:
Commissioning is required by:
Commissioning is a process activity. It spans design, construction, and occupancy.
| Activity | TAB | Commissioning |
|---|---|---|
| Scope | Measure & adjust airflow/water flow | Verify the whole system design |
| Who performs | TAB agency (AABC/NEBB) | Commissioning Authority (CxA) |
| Duration | Days to weeks | Months (design to 1-year post-occupancy) |
| Documentation | TAB report with airflow readings | OPR, BOD, Cx plan, issue log, final report |
| Standards | AABC, NEBB, SMACNA | ASHRAE Guideline 0, ASHRAE 202, LEED |
| Typical cost | $2,000–$10,000 per building | 0.5–2% of construction cost |
| Required for ENERGY STAR? | No (but recommended) | No (but recommended) |
You need TAB when:
You need commissioning when:
HECS USA provides both TAB and commissioning services:
In practice, the Commissioning Authority (CxA) should be independent from the installer and ideally from the TAB agency (to avoid conflict of interest). At HECS USA, our TAB and RCx services are performed by separate teams within the same firm to maintain independence.
TAB is typically performed once — at building turnover. If a duct or damper is modified later, partial TAB is needed for the affected zone only.
Typically not. ENERGY STAR and NGBS Green do not require full AABC TAB for single-family — they require “HVAC performance verification” which is a simpler air balance check that HECS USA performs as part of its standard inspection.
HECS USA provides TAB, residential commissioning, and HVAC performance verification across Kentucky, Indiana, Ohio, Tennessee, Illinois, and Missouri. Whether you are building a custom home or a 100-unit apartment, call (859) 983-7382 or get a quote online.